Scrum: 不同的产品所有人和项目管理员[关闭]
原标题:Scrum : Different Product owner and Project Manager [closed]
  • 时间:2012-05-27 16:49:14
  •  标签:
  • scrum
Closed. This question is off-topic. It is not currently accepting answers.

想要改进这个问题吗? 更新了问题 ,因此用于堆积溢流的

Closed 11 years ago.

我制作了两份作者的简短文件:Ken Swchaber和Jeff Sutherland。

The Product Owner is the sole person responsible for managing the Product Backlog

我看到,在正常软件开发过程中,Product owner 非常像 项目管理员

那么,什么是真正的区别, 或者只是相同的。

最佳回答

产品所有人和项目经理的情况大不相同。

在传统项目上,项目经理(如标题所暗示的那样)管理项目。

然而,在Scrum项目中,发展小组管理自己的工作。

产品所有人虽然负责最大限度地提高产品价值和发展队的工作,但是唯一负责管理产品积压的人。

产品积压管理包括:

  • Clearly expressing Product Backlog items;
  • Ordering the items in the Product Backlog to best achieve goals and missions;
  • Ensuring the value of the work the Development Team performs;
  • Ensuring that the Product Backlog is visible, transparent, and clear to all, and shows what the Scrum Team will work on next;
  • Ensuring the Development Team understands items in the Product Backlog to the level needed.

有关 产品所有人的需求 的更多细节。

问题回答

差异是微妙的,因为我们倾向于从“管理积压”一语中推断出很多。

虽然总理通常负责协调该举措应如何完成,但产品所有者则负责了解产品展示的内容,并与团队合作,确保产品清单(通常在商业术语中称为 " 特征 " )反映这一点。

在Scrum中,发展小组(由产生迭代全面递增所需的所有技能组成)负责确定如何完成选定在迭代中完成的项目。

我想你问这个是因为你对敏捷不太了解。

项目经理:他决定一切,测试人员、开发人员。。。通常不在一起交谈,他们必须与项目经理交谈,项目经理会把这个想法告诉其他人。例如:开发人员说:“我已经添加了这个功能A”。例如,项目经理会对测试人员说:“嘿,你应该为功能a添加一个单元测试”。

Product Owner : yeah, Project Manager can be a Product Owner, or, your customer can be product owner, too. It means : Product Owner : the person who can control the flow how the software is ! More over, product owner : he just looks how you work and give some talk to control the FLOW, not control your activity.





相关问题
Agile Myths and Misconceptions [closed]

What are the myths or misconceptions related to Agile? There are lot of misconceptions related to Agile that an average new comer may fall into. What are the misconceptions in the Agile world and how ...

Kanban/Scrum Boards [closed]

I m curious as to what other people use for physical Kanban/Scrum boards in their companies. I appreciate that because of sensitive business information you may not be able to provide a photo of the ...

Scrum and Project estimated time [closed]

IF the client asks me for a estimated time for completion for the whole project can this be given using Scrum? Using for instance the (dreaded) waterfall methodology I will have a technical spec to ...

How to work unestimatable tasks into a scrum sprint? [closed]

I am the scrum master for a small team of 4 developers. The project we are working on has a lot of tasks that we have never done before and cannot easily estimate in a sprint planning meeting. What ...

Writing user stories for internal technical tasks [closed]

I am attempting to manage my projects a little better so I am looking at attempting to apply some of (eventually all) the features of scrum. Looking at user stories specifically the high level format ...

热门标签